July 2023 Construction Update
Thank you for your interest in MEC internet.
Have you paid your connection fee and are waiting for
your installation? The update below shows when you can expect a call from
us to schedule your appointment. We know waiting is hard, and we appreciate
your patience. Please check your voicemails in case you miss a call from us.
We recently completed construction in these zones: Bainbridge
B-C and Clayton 1-4. Installs have begun or will begin shortly in these areas.
Here’s the latest on where we are with construction for
2023:
- Arlington: Walkout work is complete
and permitting is underway. Mainline construction is expected to begin in
Q3 2023 and home installations are anticipated to begin in Q4 2023.
- Bainbridge C: Mainline construction is complete
and home installs are just beginning.
- Bangor: Walkout work and permitting
is complete. Mainline construction has begun, and home installations are
anticipated in Q4 2023.
- Blissfield: Walkout work and permitting
is complete. Mainline construction and home installations are anticipated
to begin in Q3 2023.
- Brooklyn: Walkout work and permitting
is complete. Mainline construction is just beginning, and home
installations are anticipated to begin in Q3 2023.
- East Hartford: Walkout work and permitting
is complete. Mainline construction has begun, and home installations are
anticipated to begin in Q3 2023.
- Geneva: Walkout work is complete
and permitting is underway. Mainline construction is anticipated to begin in
Q3 2023 and home installations are anticipated to begin in Q4 2023.
- Hagar Shore: Walkout work and permitting
is complete. Mainline construction is just beginning, and home installations
are anticipated to begin in Q3 2023.
- Leroy A: Walkout work and permitting
is complete. Mainline construction is underway and home installations are
anticipated in Q3 2023.
- Leroy B: Walkout work is complete,
and mainline construction is anticipated to begin in Q3 2023 with home
installations beginning in Q4 2023.
- Manchester A: Walkout work and permitting is
complete. Mainline construction has begun, and home installations are
anticipated to begin in Q3 2023.
- Manchester B: Walkout work is complete
and permitting is underway. Mainline construction is anticipated in Q3
2023 with home installations anticipated in Q4 2023.
- Manchester C: Walkout work is complete and
permitting is underway. Mainline construction and home installations are
anticipated in Q4 2023.
- Mottville B: Walkout work is complete,
and permits are pending. Mainline construction and home installations are
anticipated to begin in Q3 2023.
- Newton A-B: Walkout work is complete
and permitting is underway. Mainline construction is anticipated in Q3
2023 with home installations starting in Q4 2023.
- Palmyra 125-127, A-B: Walkout work and permitting
is complete. Mainline construction and home installations are anticipated
to begin in Q3 2023.
- Paw Paw Lake: Walkout work and permitting
is complete. Mainline construction has begun, and home installations are
anticipated to begin in Q3 2023.
- South Hartford: Walkout work and permitting
is complete. Mainline construction is underway and home installations are
anticipated to begin in Q3 2023.
- Wakeshma A: Walkout work is complete
and permitting is underway. Mainline construction has begun and home
installations are expected in Q3 2023.
- Wakeshma B: Walkout work is complete
and permitting is pending. Mainline construction and home installations
are anticipated to begin in Q3 2023.
- WashtenawARPA_Manchester A: Walkout work is complete and
permitting is underway. Mainline construction is just beginning, and home
installations are anticipated to begin in Q3 2023.
- WashtenawARPA_Manchester B-C: Walkout work is complete and
permitting is underway. Mainline construction is anticipated to begin in
Q3 2023 with home installations anticipated in Q4 2023.
FYI: Like with all construction projects, dates
are subject to change. We send updates every month to keep you informed on
progress. Once construction is complete in an area, it can take 6-12 weeks
for installation depending on our current installation schedule.
Key Terms in the Fiber Construction Process:
Walkout Work: Involves surveying the area to decide
how to lay fiber lines.
Mainline Construction: The mainline represents the
backbone of our fiber infrastructure and carries fiber out into our
communities.
Mainline Splicing: Connects the fiber cables together
along this backbone.
Drop Construction (or Service Drop): We bring the
fiber from the mainline to your property/home and install a network interface
device (NID) on your property near the electric meter.
Drop Splice: We connect the mainline fiber to the
service drop and the fiber cables inside the NID. This is the last step before
home installation.
For more information
about the fiber construction process, please review this short video: https://www.youtube.com/watch?v=i8pMeRsnQko