June 2023 Construction Update
Thank you for your interest in MEC internet.
Have you paid your connection fee and are waiting for
your installation? The update below shows when you can expect a call from
us to schedule your appointment. We know waiting is hard, and we appreciate
your patience. Please check your voicemails in case you miss a call from us.
We recently completed construction in these zones: Bainbridge
A-B, Berrien Ext, Berrien Special Project, Deer Pointe, Eau Claire, Eau
Claire South, Kaiser Lake, Loch Erin, Mendon A, Mendon B, Nottawa A, Nottawa B,
Oronoko, Oronoko Special, Seneca 130A-D, Seneca 131A-G, Sister Lakes, South
Decatur, Tecumseh East, Tecumseh North, Tecumseh South, and Tipton. Installs
have begun or will begin shortly in these areas.
Here’s the latest on where we are with construction for
2023:
- Arlington: Walkout work is complete,
and permitting is underway with mainline construction starting in Q3 2023.
- Bainbridge C: Mainline construction is underway
and home installs are anticipated to begin in Q2 2023.
- Bangor: Walkout work and permitting
is complete. Mainline construction is just beginning, and home installations
are anticipated in Q4 2023.
- Blissfield: Walkout work is complete,
and permits are pending. Mainline construction is anticipated to begin in
Q3 2023.
- Brooklyn: Walkout work and permitting
is complete. Mainline construction is just beginning, and home
installations are anticipated to begin in Q3 2023.
- Clayton 1-4: Walkout work and permitting is
complete. Mainline construction is underway and home installations are
anticipated to begin soon.
- East Hartford: Walkout work and permitting
is complete. Mainline construction is just beginning, and home
installations are anticipated to begin in Q3 2023.
- Geneva: Walkout work is complete
and permitting is underway. Mainline construction is anticipated in Q3
2023.
- Hagar Shore: Walkout work and permitting
is complete. Mainline construction is just beginning, and home
installations are anticipated to begin in Q3 2023.
- Leroy A: Walkout work and permitting
is complete. Mainline construction is underway and home installations are
anticipated in Q3 2023.
- Leroy B: Walkout work is complete,
and mainline construction is anticipated to begin in Q3 2023.
- Manchester: Walkout work is complete
and permitting is underway. Mainline construction is anticipated in Q3
2023.
- Marshall: Walkout work is complete, and
permits are underway. Mainline construction is anticipated to start in Q4
2023.
- Mottville B: Permits are pending, and
mainline construction is anticipated to begin in Q3 2023.
- Newton: Walkout work is complete
and permitting is underway. Mainline construction is anticipated in Q3
2023.
- Palmyra 125-127, A-B: Walkout work and permitting
is underway. Mainline construction is anticipated to begin in Q3 2023.
- Paw Paw Lake: Walkout work and permitting
is complete. Mainline construction is just beginning, and home installations
are anticipated to begin in Q3 2023.
- South Hartford: Walkout work and permitting
is complete. Mainline construction is underway and home installations are
anticipated to begin in Q3 2023.
- Wakeshma A: Walkout work is complete
and permitting is underway. Mainline construction is just beginning.
- Wakeshma B: Walkout work is complete
and permitting is underway. Mainline construction is anticipated to begin
soon.
FYI: Like with all construction projects, dates
are subject to change. We send updates every month to keep you informed on
progress. Once construction is complete in an area, it can take up to 6-12 weeks
for installation depending on our current installation schedule.
Key Terms in the Fiber Construction Process:
Walkout Work: Involves surveying the area to decide
how to lay fiber lines.
Mainline Construction: The mainline represents the
backbone of our fiber infrastructure and carries fiber out into our
communities.
Mainline Splicing: Connects the fiber cables together
along this backbone.
Drop Construction (or Service Drop): We bring the
fiber from the mainline to your property/home and install a network interface
device (NID) on your property near the electric meter.
Drop Splice: We connect the mainline fiber to the
service drop and the fiber cables inside the NID. This is the last step before
home installation.
For more information
about the fiber construction process, please review this short video: https://www.youtube.com/watch?v=i8pMeRsnQko